Wednesday, September 22, 2021: The form for the east side of the new foundation is ready for concrete on Thursday. Expected delivery is 10:00 am.
September 17, 2021: Grade beam for the new foundation taking form
September 10, 2021: Great progress was made over the last two weeks as the new foundation takes form.
Friday, August 6, 2021: First pouring of concrete for the new foundation
The first pouring of concrete occurred for the first of 13 footings. A retaining wall was also constructed to protect the second footing from the constant flow of water from Silver Lake..
Friday, July 30, 2021: Excavating and constructing the form for the first of 13 concrete footings.
Friday, July 23, 2021: Establishing the lines for the new foundation
Thursday, July 22, 2021: Mobilization of the site.
Executive director Jennifer Lister and the Excav Services foundation team.