Over the last four months, significant progress was made in restoring the Roslyn Grist Mill with the completion of the restoration of the historic timbers. The structural stabilization phase of the project is expected to be completely by June 30, 2023.
Here are some highlights:
Completed Work (October 2022 to January 2023)
Planned Spring Construction (April 2023 to June 2023)
•Installation of restored and new timbers
•Install columns, braces and ties with crane
•Remove steel beams
•Remove old Bent 1 and install new Bent 1
•Lower building to new foundation with front entrance at street level
•Temporary shoring/posts
•Completion of Phase 1 Structural Stabilization