Fifteen of the 30 timber columns were re-installed in the Roslyn Grist Mill last week. A team of expert timber framers and construction workers were led by Jan Lewandoski, one of the leading timber repair experts in the world.
The restoration will be continued in May.
Eight re-installed columns on the east side.
Seven columns re-installed on the west side
Laying out Bent I (first columns and tie beams on the north side of the building) to be re-installed in May